Back
Shutterstock 2622191435 web
Decarbonisation: How Can You Create a Competitive Asset?
Back
London skyline and river thames
A New Chapter for the LPA NextGen
Find out more
GT
Written by Editor
Categories:
Share On:
Nov 27, 2026

Work begins on the Tavern Stand redevelopment at Lord’s

The redevelopment will add around 780 seats, taking capacity to 4,110, and improve accessibility and facilities for Members, spectators and players.

Substructure works are underway on the redevelopment of the 1960s Tavern Stand at Lord’s Cricket Ground. The project marks the next phase of Marylebone Cricket Club’s (MCC) Masterplan and follows the award of a fixed-price lump-sum design and build contract to FB Ellmer, which is also delivering the adjacent Allen Stand. The appointment makes FB Ellmer the first contractor to deliver consecutive stands at Lord’s.

As with the Allen Stand, G&T is providing Cost Management and Project Management services to MCC. The team helped develop the project brief, appoint the design team, and secure planning consent before guiding the design through RIBA Stage 4. G&T also led the negotiated two-stage contractor procurement process and supported MCC in finalising the contract terms with FB Ellmer.
 

“The challenge is to increase capacity for Members and spectators and provide better facilities for all users on a constrained site while maximising seating available each cricket season throughout the construction period.”

Jay Neil

Partner, G&T

The Tavern Stand occupies a narrow site between the main outfield and the tree-lined St John’s Wood Road, extending to the existing boundary wall it shares with the listed Grace Gate. In line with MCC’s sustainability objectives, the design retains the existing steel frame and foundations and introduces a new basement beneath the lower terrace. An extension at the rear provides additional accommodation and supports a cantilevered new fourth tier of seating.

The redeveloped stand has been designed to be fully accessible, with improved spectator amenities, a Changing Places facility and additional hospitality spaces. Third and fourth changing rooms and a gym will improve facilities for players.

Construction will be phased around major fixtures and aims to maximise the number of safely available seats across four seasons during the works, including provision of temporary seating on the lower terrace in 2028. G&T will continue to provide Cost Management, Project Management and Employer’s Agent services throughout the phased delivery.

G&T partner Jay Neil commented: “The challenge is to increase capacity for Members and spectators and provide better facilities for all users on a constrained site while maximising seating available each cricket season throughout the construction period. Retaining the existing structure and planning the work around the match calendar have shaped the project from the outset. We look forward to continuing to support  MCC as construction progresses.”
All images © Wilkinson Eyre Architects.

Sports, Stadia & Venues
Sports, Stadia & Venues

Sports, stadia and venues shape communities and create lasting memories. We help owners and operators maximise return on investment, balancing sustainability, technology and operational performance.

Sports, Stadia & Venues

Related News

Oct 12, 2026

Edinburgh Biomes reaches milestone as Palm Houses Reopen

By Editor
Aug 20, 2026

Grosvenor Square Reopens As Landmark Urban Garden

By Editor
Jul 03, 2026

Olympia Unveils Major New Openings as Regeneration Reaches Key Milestone

By Editor
Jun 29, 2026

London Museum to Open Landmark New Home at Smithfield This November

By Editor
Jun 26, 2026

G&T Appointed to TfL Professional Services Framework 3

By Editor
View all News Articles
Sign up

Tell us what you would like to hear about and we will send you a monthly e-shot with industry news, market intelligence, project stories, career opportunities, video content and more.

Sign up